Plan
KMIC will optimize the surrounding infrastructure to create an international standard industrial complex. The current two-lane road will be expanded into a four-lane access road connected to the Yangon-Naypyitaw-Mandalay Expressway. Water will be drawn from the Kalihtaw Dam, 18 km to the north, and purified onsite. Transmission lines will be extended from the national grid, 7 ~ 9 km to the north, and connected to an onsite substation.
Water
:
Drawing intake water from Kalihtaw Dam (12 km) Installing water purification plant
Electricity
:
Required Power: 100 MW Installing substation & Transmission & Transmission Line (Approx. 8 km)
Access Road
:
Approx. 9.4 km. Expanding into 4 lanes (Existing: 1 lane)